A Pacific Northwest highway bridge deck replacement required 45,000 headed shear studs installed in 21 calendar days. Here's how the contractor did it — and what we provided to make it happen.
A state DOT bridge deck replacement on a heavily trafficked two-lane highway. The project involved replacement of the existing concrete deck with a new composite deck on existing steel girders. The structural design called for 3/4" headed shear studs at a specific spacing along each girder.
The bridge had a hard lane closure window. Traffic control, concrete deck work, and steel prep all had to be sequenced tightly. The stud welding phase had a 21-day window — roughly 2,100 studs per day at full production.
We provided a dual-gun 256kVA generator package, pre-calibrated for 3/4" headed studs on ASTM A709 Grade 50W steel. The dual-gun configuration allowed two operators working simultaneously, effectively doubling output to 4,200+ studs per day at full pace.
The contractor's QC team maintained a detailed weld parameter log — shift start times, operator IDs, amperage, weld time, and bend test results. When a minor parameter drift was detected on day 9, the log allowed the QC team to trace exactly which studs were welded during the drift and re-test the affected area. No rework was required.
The key takeaway: a well-maintained weld parameter log is not just a compliance checkbox — it's a real-time quality control tool that saves time and rework when issues arise.